Between the closure of the line in 1993 and the commencement of Metro construction work in 2020 four civil engineering projects required the construction of new bridges.
- The first new bridge was needed for the construction of the Black Country New Road between Wednesbury and Great Bridge. This opened in 1994 and a dual-carriageway now crosses the line just a few yards south of Eagle Lane level crossing via a four-span viaduct. The extensive road works associated with this project saw Eagle Lane itself closed as a through-route to road traffic - it became a footpath.
- The second project was the opening of the first Midland Metro line in 1999. This required a new bridge to carry the ex-GWR Birmingham to Wolverhampton alignment over the South Staffs line at Wednesbury. The original bridge at the same location had long gone by the time that the Metro was built.
- Later in 1999 a new road bridge was built at Cinder Bank to take the Dudley Southern Bypass over the railway. The railway alignment was carefully preserved, but the track was removed in the vicinity of these works, and not replaced of course.
- The northern half of Wood Green viaduct, near Bescot Curve jct, was replaced by a new two-span concrete bridge in 2007. This was intended to provide road access to the parcel of land previously used by Bescot Drop Forgings, and Spear & Jackson (previously Elwell's). Before they closed these factories were accessed from St Paul's Road, Wednesbury. However this road wasn't suitable for large modern lorries because it's narrow, and bisects the High School campus. The bridge taking the South Staffs line over St Paul's Road is also too small for large artics. So a new access road was required to link the new development directly to junction 9 of the M6. This new road also needed to pass underneath the abandoned railway, hence the new bridge. In the event the site lay undeveloped until late 2013, when preparatory groundwork commenced. In February 2016 work finally began on the construction of a large Lidl distribution depot, which opened for business in the spring of 2017.
Up Dudley Siding (UDS)
This is the name for a short stretch of track on the South Staffs route between Pleck Jct and the site of Bescot Curve Jct. During 2012 and 2013 the redundant up and down Dudley lines - not used since 1993 - were relaid to a point underneath the M6 motorway. Here the lines converged into a short shunt neck, via a set of hand-operated points. The purpose of this was to provide a run-round facility for coal trains heading to and from Rugeley power station, saving them from having to go into Bescot to run-round.
Trains would arrive on the (former) Up Dudley line and stop just short of the motorway. The driver would then detach the loco, draw forward into the neck, change the points, and proceed back towards Pleck Jct via the former down Dudley line. When signalled the loco would proceed forward on the down slow line to a point just beyond the Wednesbury Road bridge at Pleck Jct. The driver would then change ends and wait for a dummy signal which controlled a move back onto the up Dudley line via a trailing crossover between the slow lines. After coupling up, the train would eventually depart "bang road" on the up Dudley line, using the same crossover under the Wednesbury Road to reach the down slow towards Walsall.
Although the requirement for this run-round facility had existed for a number of years, its provision was timed to coincide with the Walsall area re-signalling which took place in August 2013. At that point Walsall signalbox closed, and control of all the signals in the Bescot and Walsall area was transferred to the West Midlands Signalling Centre at Saltley. Although the re-signalling went ahead as planned, the Up Dudley Siding didn't become available for use until over a year later - in autumn 2014. By late 2014 coal trains were running at normal winter volumes or better, and for the most part all were using the UDS instead of running-round in Bescot.
However in April 2015 significantly higher carbon taxes became effective for the use of coal in electricity production. As a result the volumes of coal being conveyed to Rugeley - and other coal-fired stations - dipped dramatically. Stockpiles at power stations allowed the continued generation of electricity, but often at reduced output. Any suspicion that normal service might be restored during the winter of 2015/16, when stockpiles had been run down and demand on the grid would rise, turned out to be wrong. Coal trains ran to Rugeley during that winter, but at much-reduced levels. Typically only one to three loaded trains ran each day, rather than the seven to nine that might have been expected in previous years.
Then in early 2016 it was announced that Rugeley power station would close that summer. Daily coal trains ceased running altogether on Friday 19th February, only a couple of weeks after the closure had been announced. From that point the power station burnt its remaining stockpiled coal, and when that ran out in early June 2016 it closed. Only a handful of trains ran to Rugeley in the period between mid-February and early-June, and most of these were limestone for the flue-gas desulphurisation plant.
So in the end the UDS turned out to be something of a white elephant. Becoming available a year later than expected meant that its useful existence spanned the period circa November 2014 to February 2016. But in reality the normal volume of coal trains only used it in the period November 2014 to March 2015. From April 2015 to February 2016 the number of coal trains running to Rugeley was low, and wouldn't have presented much inconvenience at Bescot. And by summer 2016 the vegetation had already started to reclaim the newly laid - but now redundant - trackwork. As with the rest of the closed line it looked like nature would take it back again within a few years.
This photo was taken from the Broadway overbridge looking
towards Wednesbury on the 30th May 2017, a little over a year after the UDS fell into disuse. As can be seen vegetation had grown across both the up
and down lines, especially the latter which looked impassable at this date.
In subsequent years the vegetation was cut back, although the lines continued to be redundant. The only regular usage has been at the north end of the
up siding, which is the left-hand track in this shot. A few yards of that line, behind the camera here, acts as a reversing spur for track machines
going into the tamper siding from the Walsall station direction, or vice-versa.
Metro construction work
Construction finally commenced in the early 2020s, the old track having largely been lifted during the preceding years alongside the surveying work. The most obvious early work, aside from track-laying on the roadway in Castle Hill, Dudley, was bridge replacement on the railway alignment. This included...
- Replacment of the bridge carrying the railway alignment over Sedgley Road East (the A457) in the Coneygree area of Tipton. The original bridge here was demolished in August 2020, and newspaper reports at that time suggested it would be replaced "later next year" (i.e. 2021). In reality work was still underway on the construction of substantial concrete abutments either side of the road in August 2022, the road itself being open as a single lane controlled by temporary traffic lights at that time. Work on the new bridge itself had been "postponed until the autumn" according to the TfWM July 2022 bulletin.
- A little over 100 yards south west of Eagle Crossing (Great Bridge) the railway alignment crosses over the Walsall Canal. This bridge was replaced in May 2021, and widely trumpeted as the first new bridge to be installed as part of the Metro construction work. There were in fact two separate railway bridges over the canal at this location, the other one lies parallel and carried the connection into the sidings at Great Bridge. This second bridge is to the left in the photo below; it hasn't been replaced and remains intact.
- About 300 yards west of the Sedgley Road the railway alignment crosses over the Old Main Line of the Birmingham canal. This bridge was replaced in November/December 2021. These new canal bridges are all similar concrete and metal constructions. The metalwork is painted black, and there are walkways along the parapets, reached from track level by four or five steps.
- Half a mile north east of Eagle Crossing is Golds Hill, mid-way between Great Bridge and Wednesbury. Here the railway crosses over the Tame Valley Canal. This bridge was replaced in March 2022.
- Just south of Eagle Crossing a bridge takes New Road (the B4517) over the railway, connecting the centre of Great Bridge with Ocker Hill. This bridge deck was being replaced in July and August of 2022.
- About 400 yards south of Potters Lane, Wednesbury, the railway crosses over the Oldbury Arm of the River Tame. This bridge is also due for replacement.
- Immediately north of the River Tame bridge the ramp taking the new Metro line up to meet the original line was under construction in August and September 2022. This will be a triangular junction, allowing trams to access the Dudley route from both the Wolverhampton and Birmingham directions. The ramp will be steep and the chords connecting to the existing alignment will be tightly curved. These chords will meet the GWR alignment either side of where it crosses over the South Staffs alignment. The Metro refers to this as the "delta" junction.